10-67. B PILLAR REPLACEMENT
This task covers:
a. Removal
b.
Installation
a. Removal
Remove twelve locknuts (5), washers (4), capscrews (2), and B pillar (1) from body (3). Discard
locknuts (5).
INITIAL SETUP:
Applicable Models
M998, M998A1, M1035, M1035A1, M1035A2,
M1037, M1038, M1038A1, M1042
Tools
General mechanics tool kit:
automotive (Appendix B, Item 1)
Materials/Parts
Twelve locknuts (Appendix G, Item 76)
Manual References
TM 9-2320-280-10
TM 9-2320-280-24P
Equipment Condition
Soft top removed, if installed (TM 9-2320-280-10).
Soft top door strikers removed, if installed
(para. 10-103).
Three point seatbelt removed (para. 10-48 or
10-48.1).
b. Installation
Install B pillar (1) on body (3) with twelve capscrews (2), washers (4), and locknuts (5). Tighten
locknuts (5) to 15 lb-ft (20 Nm).
FOLLOW-ON TASKS: Install soft top, if removed (TM 9-2320-280-10).
Install soft top door strikers, if removed (para. 10-103).
Install three point seatbelt (para. 10-48 or 10-48.1).
TM 9-2320-280-20-3
Change 1
10-111