TM 9-2320-362-14&P
4-18. EES KIT INSTALLATION (Contd)
dd. Freon Lines Installation
1.
2.
3.
4.
5.
6.
Cut insulation (1) from suction hose (2) as follows:
(a) Measure 11 in. (27.94 cm) from end of suction hose (2) and
make circular cut around insulation (1).
(b) Cut insulation 22 in. (55.88 cm) lengthwise.
(c) Make another circular cut around insulation (1) at 33 in.
(83.82 cm).
Remove insulation (1) from suction hose (2).
Cut insulation (4) from discharge hose (3) as follows:
(a) Measure 33 in. (83.82 cm) from end of discharge hose (3) and
make circular cut around insulation (4).
(b) From end of discharge hose (3), cut insulation (4) lengthwise
until circular cut is reached.
Remove insulation (4) from discharge hose (3).
Install suction hose (2) through hole (6) in transmission
tunnel (5).
Install discharge hose (3) through hole (6) in transmission
tunnel (5).
4-67